report in Daily News and Analysis (January 10) spoke about a project to start a ferry service between Borivali and Nariman Point in Mumbai. The news report painted an optimistic and rosy picture of the project and sounded as if the harassed suburban rail commuters would be changing over to this mode of travel. It, however, may not be so. It may turn out to be a project to serve the elite living in the posh colonies in or around the western seashore. The common man however is certain to bear the burden of this project without enjoying its benefits. The issue is of public importance and it would need to be debated especially when public funds are intended to be used. Environmental clearance has been given by the concerned ministry and it is expected that the project may start off this year itself. The project is being implemented by the Maharashtra State Road Transport Authority. The members of the consortium, which is led by a private shipping company, are IDFC, Dena Bank, Videocon International, Hiranandani Group, KSMC Financial Services, ABS Hovercraft, UK and Gammon.

In projects of this nature, it is only the participating institutions and decision-making government authorities who will have all the relevant facts and figures. The public can at best express its views, expectations and apprehensions of the project. It is therefore necessary that the authorities disclose all the relevant information to enable the public to know what the project will mean for them.

The financial cost of the project is not disclosed; nor are the terms of funding by the bank and the infrastructure development institution involved. The private parties cannot plead commercial secrecy when public funds are likely to be used. It may be recalled that a few years back, a hovercraft service operated between Vashi and the Gateway of India. That service was wound up because it was not found to be viable. We should also remember that a few years back a private sector entrepreneur started an airconditioned bus service on several routes in the city. It was started with all fanfare. Soon it ran into financial difficulties and the state had to take it over, adding to the BEST’s woes.

A few points about the proposed ferry service are raised here in the interest of an informed debate.

  • (i) What is the total cost of the project? (ii) What is the share of each of the members of the consortium? (iii) Is the state or any of its entities contributing financially to the project or are they parting with public assets for the use of the consortium? If so, the terms thereof?
  • (iv) Has the state government agreed to give any relief or subsidy for the project? (v) Have all risks been fairly estimated and who are going to bear them? (vi) Who will be the beneficiaries – the suburban rail passengers, the gentry who use private modes of transport to travel to the city, or the elite living in the fashionable villas in the colonies abutting the shore? (vii) Who is going to foot the bill to erect the infrastructure that will be needed to build jetties, boarding and alighting bays? Is sensitive public land being handed over to private parties? (viii) What about the transport infrastructure needed for bringing prospective passengers from points near their residences to the various boarding bays? Are the passengers to rely on private transport or public transport, such as the BEST? If the latter, have any coordination arrangements been formulated with the BEST? (ix) What is the estimated fare from Borivali to the various stations? Has the affordability point been satisfied by the project providers and the decision-makers? (x) Apart
  • (Continued on p 368)

    Subscription

    Inland

    (Rs)

    Six One Two Three months year years years

    Institutions – 1250 2300 3300 Individuals 500 935 1750 2500

    Concessional Rates

    Teachers/Researchers – 685 – 1800 Students – 450 – –

    Concessional rates are available only in India. To avail of concessional rates, certificate from relevant institution is essential. Remittance by money order/bank draft preferred. Please add Rs 35 to outstation cheques towards bank collection charges.

    Nepal and Bhutan

    Institutions – 1500 – 4150 Individuals – 1250 – 3500

    Foreign

    (US $)

    Air Mail Surface Mail

    Institutions

    1yr 2yrs 3yrs 1yr 2yrs 3yrs Sri Lanka, Pakistan and Bangladesh 80 150 200 65 120 175 Other countries 150 275 375 90 170 240

    Individuals Sri Lanka, Pakistan and Bangladesh 50 90 125 30 50 75 Other countries 100 175 240 65 120 170

    All remittances to:

    Economic and Political Weekly

    Economic and Political Weekly

    Hitkari House, 284 Shahid Bhagatsingh Road, Mumbai 400 001 Phones: 2269 6072/73 Fax: (022) 2269 6072 epw@vsnl.com edit@epw.org.in Editor (December 1969-January 2004) : Krishna Raj

    Editor : C Rammanohar Reddy

    Deputy Editor : Bernard D’Mello

    Assistant Editors : Anuradha Kumar, Vimala Subramanian, Sheba Tejani Bharati Bhargava (Delhi)

    Editorial Staff : Prabha Pillai

    Editorial Consultant : Gautam Navlakha (Delhi)

    Circulation : Gauraang Pradhan (Manager), B S Sharma circulation@epw.org.in

    Advertisement Manager : Kamal G Fanibanda advt@epw.org.in

    General Manager and Publisher : K Vijayakumar

    EPW Research Foundation

    C 212, Akurli Industrial Estate, Kandivali (East) Mumbai 400 101, Phones: 2887 3038/3041 Fax: (022) 2887 3038. epwrf@vsnl.com

    Director : S L Shetty

    Economic and Political Weekly January 28, 2006

    Letters

    (Continued from p 290)

    from their membership obligations of the consortium, are the IDFC and Dena Bank granting any loans to the shipping company that is heading the consortium? What are the specific roles, functions and obligations of the MSRTC and the consortium leader – a private party? Hopefully, Dena Bank would have ensured that it is not going to add more to its non-performing assets. It will be the duty of the authorities to enlighten the public on all the above aspects.

    Any new innovative infrastructure arrangement needs to be considered in all fairness and banks and infrastructure institutions should encourage such projects. But the viability of such projects is an important aspect and we cannot give any less importance to this merely because it is a private venture. When new instruments of public-private partnership are being propagated and taken up, it is the responsibility of the government to ensure that the terms of the public-private partnership are fair and reasonable and do not result in unduly large gains to one party and onerous responsibilities for the other. In fact, the success of public-private partnerships depends on the greater dissemination of relevant information on the terms and conditions of the various agreements. Otherwise, the good instrument of the public-private partnership is likely to be a new name for public assets being transferred to private profits.

    At any rate, the state government and its organisations that are implementing this project will need to provide the public with more relevant and meaningful details so that the people can rest assured that their monies are being put to profitable use and not frittered away in some illusory project that will not benefit the common person. It is hoped that the state will fulfil this public obligation.

    S SUBRAMANYAN

    Mumbai

    Notes to Contributors

    Here are some guidelines fortake up to six to eight months from the address, day-time phone numbers andauthors who wish to make date of acceptance to appear in the email address. submissions to the journal. EPW. Every effort will, however, be made (The email address of writers in the

    to ensure early publication. Papers with Special Article, Commentary and

    Special Articles

    immediate relevance for policy would be Discussion sections will be published atEPW welcomes original research papers considered for early publication. Please the end of the article.)

    in any of the social sciences.

    note that this is a matter of editorial * Authors are requested to prepare their

    * Articles must be no more than 8,000

    judgment. soft copy versions in text formats. PDF

    words, including notes, references

    versions are not accepted by the EPW.

    and tables. Longer articles will not Commentaries

    Authors are encouraged to use UKbe processed. EPW invites short contributions to the English spellings (Writers using MS Word

  • * Contributions should be sent in a ‘Commentary’ section on topical social, or similar software could change thehard copy format accompanied by a economic and political developments. These appropriate settings in the Languagefloppy/CD version. A soft copy can should ideally be between 1,000 and 2,500 menu of the application).
  • also be sent by email. Hard and soft words and exclusive to the EPW. * Contributors are requested to sendcopy versions of articles are essential Short contributions may be sent by email. articles that are complete in all respects,for processing. including references, as this facilitates
  • * Special articles should be Book Reviews quicker processing. accompanied by an abstract of a EPW sends out books for review. It does * When there are major developments in
  • maximum of 150-200 words. not normally accept unsolicited reviews. the field of study after the first submission,
  • * Papers should not have been However, all reviews that are received are authors can send a revised version. simultaneously submitted for publication read with interest and where a book has not EPW requests writers not to send to another journal or newspaper. If the been sent out for review, the unsolicited review revised versions based on stylistic paper has appeared earlier in a different is on occasion considered for publication. changes/additions, deletions of version, we would appreciate a copy of references, minor changes, etc, as
  • Letters

    this along with the submitted paper. this poses challenges in processing.

    * Graphs and charts prepared in MS Readers of EPW are encouraged to send * All submissions will be acknowledged

    Office (Word/Excel) or equivalent comments and suggestions (300-400 words) immediately on receipt with a referenceon published articles to the Letters column. number. Quoting the reference number

    software are preferable to material All letters should have the writer’s full name in inquiries will help.

    prepared in jpeg or other formats.

    * Every effort is taken to complete early and postal address. * EPW posts all published articles on its processing of the papers we receive.

    web site and may reproduce them on CDs.

    Discussion

    Since we receive more than 35 articles Address for communication:

    EPW encourages researchers to comment

    every week and adequate time has to be Economic and Political Weekly,

    on Special Articles. Submissions should be

    provided for internal reading and external Hitkari House,

    1,000 to 2,000 words.

    refereeing. It can take up to four 284 Shahid Bhagatsingh Road, months for a final decision on whether General Guidelines Mumbai 400 001, India. the paper is accepted for publication. * Writers are requested to provide full Email: edit@epw.org.in,

    * Articles accepted for publication can details for correspondence: postal epw.mumbai@gmail.com

    Economic and Political Weekly January 28, 2006

    Dear Reader,

    To continue reading, become a subscriber.

    Explore our attractive subscription offers.

    Click here

    Back to Top